Filters
Question type

Study Flashcards

In a project network, the critical path is the sequence of activities which has the:


A) most activities.
B) most nodes.
C) most events.
D) longest duration.
E) greatest variance.

F) A) and D)
G) A) and C)

Correct Answer

verifed

verified

The standard deviation of the critical path is equal to the sum of the standard deviations of all of the activities on the critical path.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for project completion? A)  41 days B)  70 days C)  100 days D)  120 days E)  221 days What is the estimated expected (mean) time for project completion?


A) 41 days
B) 70 days
C) 100 days
D) 120 days
E) 221 days

F) C) and D)
G) B) and E)

Correct Answer

verifed

verified

The probability of occurrence of risk events is lower near the beginning of a project and higher near the end of the project since very few activities remain.

A) True
B) False

Correct Answer

verifed

verified

If an activity is determined to be on the critical path, that means that unlike activities that are not on the critical path, it will affect project:


A) direct costs.
B) performance.
C) quality.
D) conflict.
E) duration.

F) C) and D)
G) B) and D)

Correct Answer

verifed

verified

E

In order to determine the probability of timely project completion, it is sometimes necessary to take into account paths other than the critical path.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated expected (mean)  time for activity Y? A)  30 days B)  29 days C)  38 days D)  26 days E)  35 days What is the estimated expected (mean) time for activity Y?


A) 30 days
B) 29 days
C) 38 days
D) 26 days
E) 35 days

F) A) and E)
G) A) and B)

Correct Answer

verifed

verified

The earliest finish time for an activity is equal to the latest finish time minus the activity slack.

A) True
B) False

Correct Answer

verifed

verified

The costs associated with risk events tend to be lower near the beginning of a project and higher near the end of the project.

A) True
B) False

Correct Answer

verifed

verified

True

Which of the following are limitations of PERT and CPM? (I) Time estimates may include a fudge factor. (II) Important activities may be overlooked. (III) It is an after-the-fact analysis.


A) I and II
B) I, II, and III
C) I and III
D) II and III
E) I only

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity E? A)  2 days B)  3 days C)  4 days D)  16 days E)  24 days What is the estimated standard deviation in the time for activity E?


A) 2 days
B) 3 days
C) 4 days
D) 16 days
E) 24 days

F) B) and E)
G) A) and E)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity Z? A)  3 days B)  2 days C)  4 days D)  8 days E)  5 days What is the estimated standard deviation in the time for activity Z?


A) 3 days
B) 2 days
C) 4 days
D) 8 days
E) 5 days

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

Activities not on the critical path have a slack time equal to zero.

A) True
B) False

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated slack time for activity E? A)  0 weeks B)  3 weeks C)  9 weeks D)  11 weeks E)  12 weeks What is the estimated slack time for activity E?


A) 0 weeks
B) 3 weeks
C) 9 weeks
D) 11 weeks
E) 12 weeks

F) C) and D)
G) None of the above

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the estimated standard deviation in the time for activity E? A)  0 weeks B)  1 week C)  2 weeks D)  3 weeks E)  4 weeks What is the estimated standard deviation in the time for activity E?


A) 0 weeks
B) 1 week
C) 2 weeks
D) 3 weeks
E) 4 weeks

F) A) and D)
G) All of the above

Correct Answer

verifed

verified

Gantt charts are most closely associated with


A) JIT.
B) PERT.
C) MRP.
D) MRPII.
E) Six Sigma.

F) A) and D)
G) A) and B)

Correct Answer

verifed

verified

A method used for establishing a logical framework for identifying the required activities for the project is called:


A) work breakdown structurE.
B) PERT.
C) planning matrix.
D) crashing.
E) critical path analysis.

F) B) and C)
G) A) and C)

Correct Answer

verifed

verified

Consider the following work breakdown structure: Consider the following work breakdown structure:   What is the probability that the critical path for this project will be completed within 200 days? A)  0.8413 B)  0.9544 C)  0.9772 D)  0.9974 E)  0.9987 What is the probability that the critical path for this project will be completed within 200 days?


A) 0.8413
B) 0.9544
C) 0.9772
D) 0.9974
E) 0.9987

F) None of the above
G) All of the above

Correct Answer

verifed

verified

A project is represented by the following diagram: A project is represented by the following diagram:   The critical path for the network shown is: A)  a-c-g. B)  a-d-f-g. C)  a-d-h-i. D)  b-e-f-g. E)  b-e-h-i. The critical path for the network shown is:


A) a-c-g.
B) a-d-f-g.
C) a-d-h-i.
D) b-e-f-g.
E) b-e-h-i.

F) B) and E)
G) A) and B)

Correct Answer

verifed

verified

D

Activity C has an early start time of 8, an early finish time of 12, a latest start time of 13, and a latest finish time of 17. Its slack is:


A) 0.
B) 1.
C) 4.
D) 5.
E) 9.

F) B) and D)
G) A) and C)

Correct Answer

verifed

verified

Showing 1 - 20 of 113

Related Exams

Show Answer