In developing the sequence which will minimize throughput time, what is the initial job to be placed in the schedule sequence?

Correct Answer

verifed

verified

If jobs A, B, and C require two operations each, while jobs D and E require one operation each, what is the schedule sequence using the slack per operation (S/O) priority rule?

Correct Answer

verifed

verified

The quantity sent to a bottleneck operation could be split into two or more process batches to better utilize a bottleneck resource rather than process the entire batch.

A) True
B) False

Correct Answer

verifed

verified

A Gantt chart is a basic scheduling tool that is most useful in low-volume systems.

A) True
B) False

Correct Answer

verifed

verified

After the row and column reductions, what is the reduced time for assigning Rick to project D?


A) 0 hours
B) 8 hours
C) 10 hours
D) 9 hours
E) 22 hours

F) A) and D)
G) None of the above

Correct Answer

verifed

verified

Which of the following is not an example of a high-volume system?


A) aircraft manufacturing
B) magazine printing
C) petroleum refining
D) waste treatment
E) commercial donut baking

F) A) and B)
G) C) and E)

Correct Answer

verifed

verified

Given the following information concerning jobs awaiting processing at a single work center, what processing sequence will result if the critical ratio (C/R) rule is used?

Correct Answer

verifed

verified

blured image The sequence will b...

View Answer

Average completion (flow) time for a schedule sequence at a work center is:


A) the sum of processing time divided by the number of jobs
B) the sum of jobs' flow times divided by the number of jobs
C) overall flow time divided by total processing time
D) total processing time plus total late time divided by number of jobs
E) the sum of flow time plus total late time divided by number of jobs

F) B) and E)
G) B) and D)

Correct Answer

verifed

verified

Splitting a large lot after one operation beyond a bottleneck operation would reduce the overall waiting time of the bottleneck operation.

A) True
B) False

Correct Answer

verifed

verified

If he uses the earliest due date first (EDD) priority rule to schedule these jobs, what will be the average job tardiness?


A) 0 hours
B) 1.5 hours
C) 1.75 hours
D) 2 hours
E) 2.25 hours

F) D) and E)
G) None of the above

Correct Answer

verifed

verified

Job X, which has a duration of four days, is due by the close of business on Friday, December 23.Without looking at the work already scheduled on X's required resource, the scheduler schedules X to be begun on the morning of Tuesday, December 20.This is an example of __________.


A) infinite scheduling
B) finite scheduling
C) forward scheduling
D) backward scheduling
E) prioritization

F) B) and E)
G) A) and D)

Correct Answer

verifed

verified

When orders exceed our capacity, priority rules are used to select which orders will be accepted.

A) True
B) False

Correct Answer

verifed

verified

Which of the following is not a measure for judging the effectiveness of a schedule sequence?


A) average number of jobs at the work center
B) total number of jobs at the work center
C) average completion (flow) time
D) average job tardiness
E) none of the above

F) C) and D)
G) B) and C)

Correct Answer

verifed

verified

In developing the sequence that will minimize throughput time, where in the schedule sequence should job W be placed?

Correct Answer

verifed

verified

What is the optimal assignment of resources to jobs?


A) 1 to A; 2 to C; 3 to B; 4 to D
B) 1 to B; 2 to D; 3 to C; 4 to A
C) 1 to C; 2 to B; 3 to A; 4 to D
D) 1 to D; 2 to B; 3 to C; 4 to A
E) 1 to A; 2 to C; 3 to D; 4 to B

F) A) and B)
G) D) and E)

Correct Answer

verifed

verified

If these jobs were scheduled in the sequence shown, what would be the throughput time?

Correct Answer

verifed

verified

In how many different ways can she assign these consultants to these projects?


A) 4
B) 8
C) 16
D) 24
E) 256

F) B) and C)
G) A) and D)

Correct Answer

verifed

verified

If optimal sequencing through three work centers is desired, Johnson's Rule II is used rather than Johnson's Rule.

A) True
B) False

Correct Answer

verifed

verified

A basic difference between scheduling in service systems and scheduling in manufacturing systems is the random nature of requests in manufacturing systems as opposed to more uniform requests in service systems.

A) True
B) False

Correct Answer

verifed

verified

The priority rule where jobs are processed according to the smallest ratio of due date to processing time is:


A) CR
B) EEDD
C) FCFS
D) S/O
E) SPT

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

Showing 21 - 40 of 134